Objective
Confirm that product maturity, production tooling, plant processes and supplier systems support representative builds.
Universal gate mapping: Manufacturing and product readiness before representative plant builds.
- Production-intent parts and required product validation completed or on an approved path
- Process flow, PFMEA, control plan, work instructions and equipment readiness
Decision and evidence
Record the decision, the evidence reviewed, open risks, action owners and due dates. Do not treat an open issue as closed without documented verification. If a design change is needed, assess product interfaces, manufacturability, validation impact, quality documentation and affected approvals before implementation.
Use applicable APQP planning and production-part approval requirements as relevant to the product, customer and supply chain.