Do not evaluate a supplier proposal or engineering change by schedule alone. Capture what changes, what must be revalidated, what it costs, when it can be implemented and how the affected product configuration will be controlled.
QQuality
Requirements, risk, product conformity, validation coverage, acceptance criteria, control-plan updates and residual risk.
- What requirement or quality characteristic is affected?
- Which tests, inspections or approvals are needed?
- What evidence is needed to accept the change?
CCost
Tooling, engineering effort, part price, non-recurring costs, rework, scrap, logistics and assumptions behind the proposal.
- What is the 1-time and recurring cost?
- Who funds tooling, trials and additional validation?
- Are savings or cost increases quantified?
TTiming
Tooling lead time, sample availability, test duration, approval lead time, implementation date and impact on project milestones.
- When can representative samples be delivered?
- What is the critical path and recovery plan?
- What is the last safe implementation date?
PPerformance
Functional, technical and vehicle-level performance targets, constraints and validation evidence affected by the proposal.
- Which performance targets or functions may change?
- Which tests must be repeated to confirm performance?
- What measured evidence demonstrates acceptance?
Affected product scope, part numbers, revisions and configuration remain important cross-functional inputs to a QCTP assessment. The P always means Performance: functional results, technical targets and validation evidence.