APQP gate connection
Gate G5 — Ramp-up and development closure
The APQP training framework defines the final phase around ramp-up and completion of supplier-development work between PPAP acceptance and project closure. The review is planned before SOP and considers final documentation, traceability, completed validation, implemented process-risk actions, long-term capability, production capacity and plant acceptance.
- Final specifications, drawings and production control plans are up to date
- Traceability is implemented across the supply chain
- Process-risk actions are implemented and reflected in controls
- Validation results conform; capability and capacity evidence are reviewed
- Where required by the approved plan, long-term capability covers 2 production series of 30 parts each
- Remaining development actions, packaging and plant acceptance are tracked to closure
Use the approved APQP grid and applicable customer procedure for exact acceptance criteria; this public guide is a practical summary, not a substitute for controlled requirements.